Notes
Slide Show
Outline
1
Project Management Skills
  • Logistics Network Inc.
2
What is a project?
  • A project is a one-time job that has defined start and end dates, a clearly specified objective, or scope of work to be performed, a pre-defined budget, and usually a temporary organization that is dismantled once the project is complete.


  • A project is a problem scheduled for solution.
        • - J.M. Juran

3
What is project management?
  • Project management is the planning, scheduling, and controlling of project activities to achieve project objectives.
4
The Primary Objectives
of All Projects.
  • Performance
  • Cost
  • Time
  • Scope
5
Some Cautionary Notes…
  • You cannot tie down all four objectives simultaneously. If three of them are specified, the fourth must be allowed to vary.
  • All four of these variables - performance, cost, time and scope - are interdependent.
  • They all cannot be dictated at once!



6
"You must control"
  • You must control
  • scope creep!
7
The Project Life-Cycle
  • Concept
  • Definition
  • Design
  • Development
  • Application
  • Post-Completion
8
"The way a problem is..."
  • The way a problem is defined determines the solution.
9
"Beware of"
  • Beware of
    “Analysis Paralysis!”
10
Essential Elements
of a Project Plan
  • A problem statement
  • Project mission statement
  • Project strategy, together with a SWOT (Strengths, Weaknesses, Opportunities, Threats) analysis supporting it
  • Project objectives
  • Develop means of translating customer needs into solutions
  • Statement of project scope
  • A list of deliverables
  • Work Breakdown Structure
  • Schedules
  • Required resources - people, equipment, etc.
  • Control system
  • Major contributors


11
"Once the project plan is..."
  • Once the project plan is developed, it should be submitted to the stakeholders for their signatures.
12
Who is a stakeholder?
  • Anyone who has a vested interest in the project. These include contributors, customers, managers, financial people, etc.
13
"Changing the Plan"
  • Changing the Plan
14
"Make changes in an orderly..."
  • Make changes in an orderly way, following a standard change procedure.
15
"The first rule of planning..."
  • The first rule of planning is to be prepared to re-plan.
16
"What is planning"
  • What is planning?
17
Planning is the answering of the following questions:
  • What must be done?
  • How should it be done?
  • Who will do it?
  • By when must it be done?
  • How much will it cost?
  • How good does it have to be?
18
Cardinal Rule of Planning
  • The people who must implement a plan should participate in preparing it.
19
Project Planning Steps
  • Define the problem to be solved.
  • Develop a mission statement followed by statements of major objectives.
  • Develop a project strategy.
  • Write a scope statement to define project boundaries.
  • Develop a Work Breakdown Structure (WBS)
  • Using the WBS, estimate activity durations, resource requirements, and costs.
  • Prepare the project master schedule and budget.
  • Set up the project notebook.
  • Get the plan signed off by all project stakeholders.


20
The Mission Statement
  • A mission statement provides the basis for which goals and objectives can be set and for making decisions, taking actions, etc.
21
A mission statement should answer these three questions
  • What do we do?
  • For whom do we do it?
  • How do we go about it?
22
Objectives
  • Should be specific
  • Should be measurable
  • Must be verifiable
  • Fit higher level organization objectives
  • Should be stated in terms of deliverable items
  • Must be comprehensible
  • Should be time-limited
  • Should be attainable
  • Should specify a single end result


23
Don’t confuse tasks with objectives!
  • An objective is a desired end-state.
  • Tasks are those actions taken to arrive at the final destination.
24
Developing Project Strategy
  • What are we going to do?
  • How are we going to do it?
25
SWOT Analysis
  • Strengths
  • Weaknesses
  • Opportunities
  • Threats
26
SWOT Analysis
  • What Strengths do we have? How can we take advantage of them?
  • What Weaknesses do we have? How can we minimize their impact?
  • What Opportunities are there? How can we capitalize on them?
  • What Threats might prevent us from getting there?
  • For every obstacle identified, what can we do to overcome or get around it?


27
Work Breakdown Structure (WBS)
  • The Work Breakdown Structure (WBS) provides a tool for planning the what, including estimates of resource requirements, activity durations and costs.
28
 
29
"The objective of all project..."
  • The objective of all project planning should be to develop a plan that is realistic, so that managers can make decisions as to whether to do the work.


30
"A Work Breakdown Structure does..."
  • A Work Breakdown Structure does not show the sequence in which work is performed! Such sequencing is determined when a schedule is developed.
31
10 Project Management Factors
  • Project Mission
  • Top Management Support
  • Project Schedule/Plan
  • Client Consultation
  • Personnel
  • Technical Tasks
  • Client Acceptance
  • Monitoring and Feedback
  • Communication
  • Troubleshooting


32
Four Stages of the Project Life-Cycle
  • Conceptualization
  • Planning
  • Execution
  • Termination
33
"Project mission and client consultation..."
  • Project mission and client consultation should be the most important predictors of project performance.
34
What determines project success?
  • Did the project attain its goals?
  • Was it done on time?
  • Was it done within budget?
  • Was the client satisfied?
35
Causes of project failure.
  • Failure to properly define the problem.
  • Planning was based on insufficient data.
  • The people who must do the job are not involved in planning it.
  • No one is in charge.
  • Project estimates are best guesses, made without consulting historical data.
  • Resource planning was inadequate.


  • People don’t see themselves as working on one team.
  • People are constantly pulled off the project or reassigned with no regard for impact.
  • The project plan lacks detail.
  • The project is not tracked against the plan.
  • People lose sight of the original goal.
  • Senior managers refuse to accept reality.
  • Ballpark estimates become official targets.