|
1
|
|
|
2
|
- A project is a one-time job that has defined start and end dates, a
clearly specified objective, or scope of work to be performed, a
pre-defined budget, and usually a temporary organization that is
dismantled once the project is complete.
- A project is a problem scheduled for solution.
|
|
3
|
- Project management is the planning, scheduling, and controlling of
project activities to achieve project objectives.
|
|
4
|
- Performance
- Cost
- Time
- Scope
|
|
5
|
- You cannot tie down all four objectives simultaneously. If three of them
are specified, the fourth must be allowed to vary.
- All four of these variables - performance, cost, time and scope - are
interdependent.
- They all cannot be dictated at once!
|
|
6
|
- You must control
- scope creep!
|
|
7
|
- Concept
- Definition
- Design
- Development
- Application
- Post-Completion
|
|
8
|
- The way a problem is defined determines the solution.
|
|
9
|
- Beware of
“Analysis Paralysis!”
|
|
10
|
- A problem statement
- Project mission statement
- Project strategy, together with a SWOT (Strengths, Weaknesses,
Opportunities, Threats) analysis supporting it
- Project objectives
- Develop means of translating customer needs into solutions
- Statement of project scope
- A list of deliverables
- Work Breakdown Structure
- Schedules
- Required resources - people, equipment, etc.
- Control system
- Major contributors
|
|
11
|
- Once the project plan is developed, it should be submitted to the
stakeholders for their signatures.
|
|
12
|
- Anyone who has a vested interest in the project. These include
contributors, customers, managers, financial people, etc.
|
|
13
|
|
|
14
|
- Make changes in an orderly way, following a standard change procedure.
|
|
15
|
- The first rule of planning is to be prepared to re-plan.
|
|
16
|
|
|
17
|
- What must be done?
- How should it be done?
- Who will do it?
- By when must it be done?
- How much will it cost?
- How good does it have to be?
|
|
18
|
- The people who must implement a plan should participate in preparing it.
|
|
19
|
- Define the problem to be solved.
- Develop a mission statement followed by statements of major objectives.
- Develop a project strategy.
- Write a scope statement to define project boundaries.
- Develop a Work Breakdown Structure (WBS)
- Using the WBS, estimate activity durations, resource requirements, and
costs.
- Prepare the project master schedule and budget.
- Set up the project notebook.
- Get the plan signed off by all project stakeholders.
|
|
20
|
- A mission statement provides the basis for which goals and objectives
can be set and for making decisions, taking actions, etc.
|
|
21
|
- What do we do?
- For whom do we do it?
- How do we go about it?
|
|
22
|
- Should be specific
- Should be measurable
- Must be verifiable
- Fit higher level organization objectives
- Should be stated in terms of deliverable items
- Must be comprehensible
- Should be time-limited
- Should be attainable
- Should specify a single end result
|
|
23
|
- An objective is a desired end-state.
- Tasks are those actions taken to arrive at the final destination.
|
|
24
|
- What are we going to do?
- How are we going to do it?
|
|
25
|
- Strengths
- Weaknesses
- Opportunities
- Threats
|
|
26
|
- What Strengths do we have? How can we take advantage of them?
- What Weaknesses do we have? How can we minimize their impact?
- What Opportunities are there? How can we capitalize on them?
- What Threats might prevent us from getting there?
- For every obstacle identified, what can we do to overcome or get around
it?
|
|
27
|
- The Work Breakdown Structure (WBS) provides a tool for planning the what,
including estimates of resource requirements, activity durations and
costs.
|
|
28
|
|
|
29
|
- The objective of all project planning should be to develop a plan that
is realistic, so that managers can make decisions as to whether to do
the work.
|
|
30
|
- A Work Breakdown Structure does not show the sequence in which work is
performed! Such sequencing is determined when a schedule is developed.
|
|
31
|
- Project Mission
- Top Management Support
- Project Schedule/Plan
- Client Consultation
- Personnel
- Technical Tasks
- Client Acceptance
- Monitoring and Feedback
- Communication
- Troubleshooting
|
|
32
|
- Conceptualization
- Planning
- Execution
- Termination
|
|
33
|
- Project mission and client consultation should be the most important
predictors of project performance.
|
|
34
|
- Did the project attain its goals?
- Was it done on time?
- Was it done within budget?
- Was the client satisfied?
|
|
35
|
- Failure to properly define the problem.
- Planning was based on insufficient data.
- The people who must do the job are not involved in planning it.
- No one is in charge.
- Project estimates are best guesses, made without consulting historical
data.
- Resource planning was inadequate.
- People don’t see themselves as working on one team.
- People are constantly pulled off the project or reassigned with no
regard for impact.
- The project plan lacks detail.
- The project is not tracked against the plan.
- People lose sight of the original goal.
- Senior managers refuse to accept reality.
- Ballpark estimates become official targets.
|