Example Work Breakdown Structure (WBS)
Implement
Cycle Time Management (CTM) Program
1.
Education/Training
1.1 Coordinators
1.1.1 Implementation Tools
1.2 Approval Team/Planning Team
1.2.1 CTM General Awareness
1.2.2 Team Based Workplace
1.2.3 New Role of
Manager/Supervisors
1.2.4 Project Management
1.2.5 Pull Manufacturing
1.3 All Manufacturing Personnel
1.3.1 CTM General Awareness
1.3.2 Team Based Workplace
1.3.3 Pull Manufacturing
2.
Analyze Present Processes/Practices
2.1 Brainstorm for CTM Opportunities
2.2.Process Map Each Manufacturing
Division
2.3 Establish Baseline of Cycle Time &
Costs for Each Manufacturing
Division
2.4 Establish Entitlement of Cycle Time
& Costs for each Manufacturing
Division
3.
Develop Evolution Plan
3.1 Select Program Leaders
3.2 Select Project Leaders
3.3 Select Projects to be a Part of
Evolution Plan
4.
Present & Execute Evolution Plan
4.1 Present Evolution Plan to Approval
Team
4.2 Prioritize Approved Projects
4.3 Staff Approved Projects
4.4 Appoint Project Leaders